A WinACC view of the future of nuclear power in the UK
Background
Can the UK provide for its future energy needs
without recourse to nuclear power?
13.8% of UK s electricity was produced by nuclear
power in 2023[1].
In 2015 the UK relied on sixteen nuclear reactors
on nine sites to supply 22% of its electricity demand.[2] By June 2024 the UK had four twin
advanced gas-cooled reactor (AGR) power stations, and Sizewell B, a single
pressurised water reactor (PWR) power station. In December 2024, EDF, who
manage all of the UK s existing reactors, said that Heysham
2 (Lancashire) and Torness (East Lothian) will keep
producing zero-carbon electricity for an additional two years to March 2030
while Heysham 1 (Lancashire) and Hartlepool (Teesside) will produce power until
March 2027, an extension of one year [3].
Sizewell B is currently due to close in 2035[4].
In addition, construction of Hinkley Point C,
partly funded by France and China, commenced in 2017. It comprises two PWRs, which will
be capable of generating 3,260 MW of secure, low-carbon electricity for
60 years [5]. It has suffered delays and cost escalation, and is unlikely to be producing electricity
before 2030[6],
five years later than originally planned. Sizewell C, following the same design as
Hinkley Point C, has been given the go ahead by government, subject to
sufficient funding being available. By the end of 2024 full funding was still
not available. Each of these, if producing for 80% of the time, is equivalent
to about 7.5% of the total electricity produced in 2023; so potentially 15%
together. However, total electricity demand is predicted to rise significantly
as electric cars and heat pumps, in particular, become more common.
The
previous government was keen to encourage private companies, and even other
countries, to build new nuclear power stations to help fill the potential
looming energy gap. The Manifesto of the new Labour government shows that it is
in favour of nuclear power also[7].
In July 2024, the new DESNZ Secretary of State said that the government would make
Britain a clean energy superpower with zero carbon electricity by 2030 [8]. However, there is insufficient time for additional nuclear to play its part
in that time frame.
In September 2024, the government picked four
companies to proceed to the next stage of negotiations for support to develop
small modular nuclear reactors (SMRs) in the UK[9].
An SMR is a small nuclear reactor producing anything from 10 megawatts (MW) to
300 MW of power. By comparison, a medium sized solar farm may have a peak
output of some 25 MW. They can be constructed mostly from modules made in a
factory, which can mass produce elements of the reactor, thus bringing down
cost. Most of the reactor can be transported from a factory to the site and
assembled there far more quickly than the large one-off construction used for a
traditional nuclear power station. An advantage they have over other power
sources is that they need a much smaller area of land than for equivalent renewable
energy installations. However, there are only two or three currently in
operation in the world, in Russia and China[10].
It seems likely to be some time before their possible economies of scale bring
down the cost of nuclear power in the UK.
Why
is nuclear power still under consideration?
The
are two major reasons.
Firstly,
it can supply a reliable base load; valuable while most renewable energy
sources suffer from intermittency problems (it s not always sunny, nor windy).
Secondly,
it is a fairly low carbon source of electricity; about
which, more below.
Another
reason, less well publicised, is that the huge spinning turbines of large
nuclear power stations hold their speed in the face of small national
fluctuations, providing stability of frequency to the grid and preventing
equipment damage[11].
This is becoming increasingly important as most current renewable energy
sources lack this spinning inertia.
However,
several scenarios of the UK s future energy supply suggest that nuclear energy
is not a necessary part of the supply.[12],[13],[14],[15] So can the UK provide for its
future needs without nuclear energy and, if so, should it do so?
Questions to be
answered
To assess the UK s future need for nuclear power
the following questions need to be answered:
1. How
practical is it to rely on a new generation of nuclear power stations to meet
an electricity demand which is likely to increase in the future as gas and oil
usage reduces?
2. How
much would nuclear power contribute to the UK s greenhouse gas emissions?
3. What
are the risks of continuing to depend on nuclear power?
4. Are
there adequate, alternative, non-greenhouse gas emitting, sources of
electricity?
How practical is
it in the long-term to rely on nuclear power stations?
Nuclear
Fuel
A
conventional one-gigawatt nuclear power station consumes approximately 200
tonnes of uranium a year, which must be extracted from ores which range between
about 20% down to around 0.03% uranium for the best of the low-grade ores.[16] ,[17] Thus,
nuclear power normally depends on access to a significant supply of
sufficiently rich uranium ores; it is therefore not renewable because the
Earth s resources are finite. Although low-grade ores, in the form of granite
for example, are widespread they are not rich enough to be exploited
economically in today s world.
A
nuclear power station typically has a design life of 30 40 years[18],
but the actual life can often be extended. A vital part of the planning process
is the availability, and cost, of fuel for that time period.
Planners and funders must therefore make difficult decisions, as discussed
below.
A
big problem is that it is notoriously difficult to assess the quantity of
reserves [A] of
many minerals in the future; as more sources tend to be discovered, technology
for refining improves, and the economics surrounding them change. For
example, the International Copper Association says that since 1950 there
has always been, on average, 40 years of copper reserves and over 200 years of
resources left [19].
The
World Nuclear Association[20] estimates that the world’s present measured resources of uranium (6.1 Mt)
in the cost category less than three times present spot prices and used only in
conventional reactors, are enough to last for about 90 years".
These estimates are based on current demand. If demand increases then supplies may run out sooner. However, they also state that this timeframe represents a higher level of assured resources than is normal for most
minerals .
A
Nuclear Energy Agency and International Atomic Energy Agency report of 2020[21] says that Identified recoverable (uranium) resources, including
reasonably assured resources and inferred resources, are sufficient for over
135 years .. assuming 2019 rates of consumption.
This time frame will clearly reduce as demand increases; and it takes no
account of cost constraints.
Less
optimistically, the US Geological Survey, with others, wrote in 2013[22] that At 2010 rates of consumption, uranium resources identified in
operating or developing mines would fuel the world nuclear fleet for about 30
years
An
added complication is that in 2022, over 40% of uranium was
produced in Kazakhstan[23],
an unstable country, making availability (and hence prices) highly
unpredictable.
Some
argue that technology will find a way to use low-grade ores, almost
irrespective of the cost involved, because of the huge capital investment
already made in nuclear power stations. However, such arguments do not
recognise the implications of the associated greenhouse gas emissions. Today, possibly 46% of the greenhouse gases emitted
by a nuclear plant are from the extraction, processing and transport of uranium[24]. Some researchers
have found that using poor ores containing less than 0.02% uranium oxide (U3O8)
to produce fuel for nuclear reactors could lead to the emission of
more greenhouse gases per unit of electricity generated than natural gas-fired
plants! This is the so-called CO2 trap.[25] How soon this will happen will depend on future global demand and on future
discoveries and grades of uranium ores, but estimates suggest it will happen
sometime in the second half of the 21st century.
Thorium is about three times as abundant in the Earth s crust as uranium
but occurs in low concentrations in the ocean because thorium oxide is
insoluble.26 The thorium cycle has
advantages, not least that in theory the fuel can be almost completely
converted into heat, and therefore generates less waste. In addition the radioactive decay of the waste is much
faster than for spent uranium fuel. But the thorium cycle needs other
fissile material to initiate the chain reaction and one of the intermediary
products – Pa-233 (protactinium-233) – is a strong neutron absorber which
slows the reaction. Interest in this
fuel cycle has largely waned since the late 1980s, except in India.
Nuclear reactors currently have lifetimes of 30-40
years, although the lifetimes of some reactors have apparently been extended to
60 years. Building one more generation of nuclear power stations appears to be
the limit using current estimates of ore supply (ie. resources), and will help to provide a solution to fill the energy
gap until renewable technologies, smart grids,[B] energy storage and adequate interconnectivity are available on a large-scale.
A thorium nuclear fuel cycle is also possible. This
cycle is being tested in India but is no longer being investigated elsewhere. This
appears to be a relatively immature technology not yet ready for deployment to
mitigate climate change.
Planning and construction
However, the time required to actually
build and commission a nuclear power station also needs to be
considered. In Europe there are two examples of building the third generation
European Pressurised Water Reactor (EPR). The Olkiluoto 3 reactor in
Finland should have taken four years to build. It was started in 2005 and
commenced operating in 2023.[29] The construction of a second EPR reactor on that site was cancelled in 2015.
Similarly, construction of the Flamanville reactor in
France was started in December 2007, with a planned five-year construction
period, and went into operation in late 2024.
If time for design and planning consent is
included, then any decision taken today to build a nuclear power station in the
UK is in danger of ending up with a reactor that is running out of fuel before
the end of its life.
Fast breeder reactors use uranium sixty times more
efficiently than pressurised water reactors (PWRs). They consume
some of the waste plutonium and partly burnt uranium fuel from PWRs and produce
yet more plutonium-239. The Russian BN-600 fast breeder reactor has operated
since 1981 and a new version, the BN-800, has been in operation in Russia since
2014[30].
However,
an international review of fast breeder reactors in 2010 concluded After
six decades and the expenditure of the equivalent of tens of billions of
dollars, the promise of breeder reactors remains largely unfulfilled and
efforts to commercialize them have been steadily cut back in most countries and The breeder reactor dream is not dead but it has receded far into
the future. [31] Currently, in Europe and the USA such reactors are still at the design stage.[32]
An important factor that needs to be considered in
the rational planning of any energy source, including nuclear power, is the energy return on energy invested (EROI).
This can be defined as the delivered energy divided by the total energy that
has been invested to produce that energy. Thus, an energy source with an EROI
less than 1 produces less energy than it consumes. It is probable that a
nation s principal power source must have an EROI in excess
of 10 to maintain anything approaching the complexity of our present
society.[33]
It appears that the EROI of nuclear power depends
on numerous factors and is hard to calculate. It has been suggested that it is
unlikely to exceed 10 or 11.[34]
For
any energy source it is also necessary to consider the energy break even time, which is the time taken to pay back the
energy invested in developing a source with the cumulative energy supplied by
that source. Energy break even time is important, because, without
massive subsidies, investors are unlikely to be interested in financing schemes
in which the energy payback time exceeds five years.
According
to a detailed life-cycle analysis, pressurised water reactors (PWRs)
have an energy payback-time of 6.5 years.[35] As PWRs have a projected lifetime of no more than 40 years the maximum
estimated EROI over this period can be estimated as (40)/6.5 = 6.15. However,
it can be argued that this estimate is conservative in that it relies on
results from an earlier generation of less efficient PWRs and takes no account
of potential lifetime extensions.[36]
Against this it has been argued that the EROI for
future nuclear power sources does not take into consideration the decline in
net energy caused by a switch to progressively lower grades of uranium ore
driven by the depletion of the best ores[37].
Further, it could be argued that even if the EROI could be increased to 10,
this would not, as we have observed above, be enough for a principal energy
source to support our society.[38]
Nuclear power in UK is expensive. At the end of
2023 the price for Hinkley Point C electricity was predicted to be 128.09 per
MWh, when it starts producing; but this is likely to rise.[39] Meanwhile, according to DESNZ[40],
the prices for projects to be commissioned in 2025 are likely to be:-
CCGT
(gas) 114 per MWh
Offshore
wind 44 per MWh
Onshore
wind 38 per MWh
Large
scale solar 41 per MWh
How will nuclear
power contribute to the reduction of UK s greenhouse gas emissions?
Nuclear energy is called clean or low carbon in
the sense that the marginal greenhouse gas emissions from generating an
additional kilowatt.hour of
energy are close to zero.
However, such statements take no account of the
emissions generated by building a nuclear power station, mining, processing and
transporting ores and enriching the uranium-235 content, manufacturing fuel
rods and, eventually, decommissioning the power station and safely disposing of
the waste, particularly the high-level waste.
In recent years detailed life-cycle analyses of the
production of energy by nuclear power stations have led to a range of estimates
from 8 to 64 g CO2 per kWh.[41] A report for EDF, who operate Torness station, in UK, calculate lifetime emissions of
16.5 g CO2 per kWh.[42] These figures cover a large range, and demonstrate the difficulty of remotely
accurate assessments.
For comparison, a 2014 life cycle analysis of
offshore wind arrays came up with emissions of 18 to 31 g CO2 per
kWh[43];
while a more recent one for solar photo voltaic systems calculated emissions as
14 to 73 g CO2 per kWh[44].
The range of all these figures demonstrates how difficult it is to compare
them. But suffice to say that they are definitely
significantly lower than those from coal or gas.
So nuclear power may not be the lowest carbon
technology available today to help meet the 81% reduction in UK greenhouse gas
emissions from 1990 levels by 2035, which was announced by the Prime Minister
at COP 29. Although far less than coal
or gas-fired power stations, even when such stations are fitted with carbon
capture and storage (CCS), their emissions are not insubstantial and appear to
be comparable with those from wind and solar photovoltaic.
A new generation of nuclear power stations could
then provide a solution in supplying baseload electricity, at least until
renewable technologies and the necessary accompanying grid solutions, including
energy storage, are sufficiently well established.
What are the risks
of nuclear power?
Nuclear power poses risks around accidents,
terrorism and waste disposal. These risks are compounded as more nuclear power
stations are built in more countries.[45] Here risks are only considered qualitatively because there is so much
uncertainty in estimating the risks quantitatively.
First, there is potential for lethal, widespread,
extremely costly and long-lasting damage from any nuclear accident. In spite of a relatively safe record over the years, nuclear
power stations will always be susceptible to human error and unexpected events,
even with modern technology (Three Mile Island 1975, Chernobyl 1986, Thorp 2005
and Fukushima 2011 are examples of accidents). Having said this, designs have been refined over time, and more safety
measures are now included. In particular, duplicate emergency
cooling systems are now used; and passive emergency cooling systems are
emerging, that require no external power to operate[46].
Second, terrorists could acquire material from
nuclear programmes to build a nuclear weapon or a dirty bomb (one that
contaminates a wide area around the site of a conventional explosion with
radioactive material). Either scenario could lead to the death, immediate or
delayed, and injury of a very large numbers of people. Terrorists may also
directly attack a nuclear facility with unpredictable but probably dire
consequences.
The third risk centres on high-level waste (HLW)
produced from waste fuel and the decommissioning of power stations. What right
do we have to leave this hazard for thousands of future generations? The UK
already has about 1,500 m3 of high-level liquid waste at Sellafield[47].
A 1 GW reactor produces about 0.5 m3 (5 tonnes) of solid HLW per
year, so the annual increase in volume of HLW from a new generation of reactors
is likely to be relatively small.[48] However, in spite of extensive research over at least the last 30 years, no
acceptable underground site in the UK has been identified where high level
waste can either be safely stored or disposed of. Plutonium-239, found in
irradiated fuel, has a half-life of 24,400 years and consequently will remain
hazardous for around 250,000 years. It decays into uranium-235 with a half-life
of 710,000 years.[49] Although the hazard remains for millions of years, it is generated, in theory,
by a relatively small volume (less than a 22 metre cube of high-level and spent
fuel waste for the UK so far) yet it has to be broken up into safe, smaller
volumes which have to be isolated from the biosphere for many thousands of
years.
In summary, it is hard to fully and quantitatively
assess the risks posed by nuclear power, particularly in comparison with other
sources of energy. Many people, including voters, feel deeply uneasy at the
prospect of an expanding nuclear power industry. Fear of radioactivity and
distrust of the nuclear industry among the general population are just as
likely to play a significant role in any political decision about nuclear power
as the arguments presented here.[50]
Are there
adequate, alternative, low carbon sources of electricity?
The answer to this question is undoubtedly a
qualified yes , depending on how energy demand can be reduced, how energy can
be used more efficiently in future, how it can be stored, and on whether
renewable sources can be installed fast enough. The UK is investing strongly in renewables. In
2023 renewables, mainly wind, bioenergy and solar, delivered 46.4% of the UK s
electricity generation.[51] It must be remembered, though, that electricity production comprises only around
15% of UK s total energy consumption.
Renewable energy means that the energy source is
infinite on a human timescale, free and largely derived from the Sun or the
Moon s rotation about the Earth. Renewable and well-tested technologies in the
form of onshore and offshore wind turbines, hydroelectricity, tidal barrages,
and photovoltaic panels already exist. Some have operated for decades; some
continue to be improved. New technologies in the form of wave and tidal current
generators are being developed.
Although some embodied greenhouse gas emissions
will be involved in the manufacture and construction of renewable energy
equipment, the life-time emissions from such technologies per unit of energy
produced are estimated to be lower than for fossil-fuel derived energy.
Renewable energy also has the huge advantage that the fuel is free and not
susceptible to price fluctuations, nor imports.
However, nuclear power stations have one big
advantage over renewable sources in that in principle they can deliver baseload
electricity i.e. the supply that is required to satisfy a demand that exists
around the clock. In the twelve months to mid-October 2024 the UK baseload was
about 25 GW which is around 60% of the peak demand in the same period.[52]
But in 2023, as already mentioned, nuclear supplied
only 13.8% of the demand for electricity, and the installed nuclear capacity is
subject to planned power station closures. A national energy supply based
predominantly on renewables might struggle, even with a smart grid, to supply
the required baseload unless backed up by an efficient form of energy
(electricity) storage and strong interconnectivity with other countries.
Finally, many advocate the use of nuclear fusion to
generate electricity. Nuclear fusion aims to reproduce the fusion reactions
that take place in the Sun. The International Thermonuclear Experimental Reactor (ITER) is being built over 10
years at Cadarache, France, where 35 nations are collaborating to create a
fusion reactor. ITER plans to create the project’s First Plasma by 2035 and to
reach full fusion power several years after that.[53] ITER is seen as the bridge toward a first
plant that will demonstrate the large-scale production of electrical power. This might be a feasible way to generate electricity in the
second half of the 21st century but today, unfortunately, it remains
a technology that is unproven at a useful scale.
Conclusions
The UK faces a looming energy gap, when demand will
exceed home grown supply, which presently is filled by imported energy. Existing
nuclear reactors will mostly be phased out by 2030. Hinkley Point C should be
producing electricity by 2030; and construction of Sizewell C has been approved
by the government, subject to sufficient funding, which, as of December 2024,
has not yet been committed. The government is showing interest in the unproven
SMR technology. However, as described above, nuclear power is not renewable nor
free of greenhouse gas emissions, nor cheap.
Two possible conclusions can be reached from the
above discussion which are at opposite ends of a spectrum of views.
1) A
nuclear energy proponent will argue that one more generation of new nuclear
power stations will help to fill the energy gap until renewable energy (or
possibly nuclear fusion) is sufficiently developed to take over entirely. It
will be particularly important as a supplier of base load, which most
renewables can t supply. It will be maintained on the assumption that new
uranium reserves will be found, or fuels can be created using the fast breeder
fuel cycle. The risks will be considered as worth taking and the argument will
emphasise the increasing reliability, safety and security of nuclear power stations,
while downplaying the high-level waste disposal problem.
2) A
nuclear energy sceptic will argue that the long time required to plan and
construct a new generation of nuclear power stations (some fifteen to twenty
years) will be too late to fill the energy gap. In addition, such power
stations may come on stream in the UK only as global supplies of uranium fuel
start to dry up and/or their exploitation generates more greenhouse gas than
gas-fired power stations (the carbon dioxide trap). The argument will be that
it seems inescapable that efforts and financial resources would be better spent
on expanding existing, well tried, renewable energy technologies, the lifetimes
of which will not be constrained by any depletion of their fuel . Lastly,
nuclear power carries the risk of serious accidents, will potentially bequeath
hazardous waste to thousands of future generations and is open to terrorist
attack.
Perhaps, because of the need to decarbonise the
grid quickly, the long time required to complete a new nuclear power station,
together with the perceived risks, will count against further nuclear energy.
Whatever decision is taken, there is an urgent need for a low carbon source of
base load power within the next five years.
Bob
Whitmarsh, 1 July 2016
Updated
2025 by Brian Shorter
[A] A mineral resource is a concentration of minerals that have been identified and measured with reasonable certainty but have not yet been proven to be economically viable for extraction; while a reserve is a portion of a mineral resource that has been demonstrated to be economically and legally extractable.
[B] A smart grid is an electrical grid that uses computers and other technology to gather and act on information, such as information about the behaviours of suppliers and consumers, in an automated fashion, to improve the efficiency, reliability, economics and sustainability of the production and distribution of electricity. From http://en.wikipedia.org/wiki/Smart_grid.
[1] UK ENERGY IN BRIEF 2024, Department for Energy Security and Net Zero
[2] Anon (IMechE). ENGINEERING THE UK
ELECTRICITY GAP. London: Institution of Mechanical Engineers, 2016.
[3] https://www.edfenergy.com/media-centre/edf-confirms-boost-uks-clean-power-targets-nuclear-life-extensions
[8] https://www.gov.uk/government/news/energy-secretary-ed-miliband-sets-out-his-priorities-for-the-department
[12] MacKay,
D. J. C. (2008). Sustainable energy – without the hot air. Cambridge,
UIT although in the last days of his life (he died in April 2016) he remained
convinced that nuclear power would continue to be essential; http://www.theguardian.com/environment/2016/may/03/idea-of-renewables-powering-uk-is-an-appalling-delusion-david-mackay
[13] Kemp,
M. and J. Wexler (2010). ZERO CARBON BRITAIN 2030 A NEW ENERGY STRATEGY: The
second report of the Zero Carbon Britain project. Machynlleth, CAT: pp.384.
[14] Helweg-Larsen,
T. and J. Bull (2007). Zero carbon Britain. Machynlleth, Public Interest
Research Centre, Centre for Alternative Energy: 105 pp.
[15] Anon.
(2012). Electricity System: Assessment of Future Challenges – Summary. London,
DECC: pp.12.
[17] http://www.world-nuclear.org/information-library/nuclear-fuel-cycle/uranium-resources/supply-of-uranium.aspx
[19] https://internationalcopper.org/sustainable-copper/about-copper/cu-demand-long-term-availability/
[20] https://world-nuclear.org/information-library/nuclear-fuel-cycle/uranium-resources/supply-of-uranium
[21] https://www.oecd-nea.org/upload/docs/application/pdf/2020-12/7555_uranium_-_resources_production_and_demand_2020__web.pdf
[25] Fig. G.18 in http://www.stormsmith.nl/
[26] MacKay,
D. J. C. (2008). Sustainable energy – without the hot air. Cambridge,
UIT.
[27] Fleming,
D. (2007). The lean guide to nuclear energy: A life-cycle in trouble.
London, The Lean Economy Connection, p.27.
[29]http://www.theecologist.org/News/news_analysis/2859924/finland_cancels_olkiluoto_4_nuclear_reactor_is_the_epr_finished.html
[30] https://wna.origindigital.co/information-library/current-and-future-generation/fast-neutron-reactors
[31] Cochran, T. B., H. A. Feiveson, et al. (2010).
Fast Breeder Reactor Programs: History and Status, International Panel on
Fissile Materials: pp.128.
[32] https://www.neimagazine.com/advanced-reactorsfusion/time-for-a-new-focus-on-fast-reactors-10380132/?cf-view
[33] Charles A. S. Hall and Kent A. Klitgaard (2012) Energy and the Wealth of Nations: Understanding the Biophysical
Economy , Springer
[34] http://georgewashington2.blogspot.co.uk/2011/04/us-wastes-more-energy-than-it-uses.html and Hall, Charles and Bobby Powers. The Energy Return of Nuclear Power.
State University of New York. April 22, 2008.
[35] Lenzen,
M. (2008). Life cycle energy and greenhouse gas emissions of nuclear energy: A
review. Energy Conversion and Management 49: 2178-2199.
[36] Pers. Comm. Alexandre Poisson, McGill
University, April, 2012.
[38] For comparison, in 2006 onshore US wind
turbines had an EROI of around 20 (www.eoearth.org/article/Energy_return_on_investment_(EROI)_for_wind_energy) and in 2009 PV systems had an EROI of about
6.6
(www.eoearth.org/article/Energy_return_on_investment_(EROI)_for_photovoltaic_energy).
[39] enewable-energy-industry.com/news/world/article-6502-new-hinkley-point-c-nuclear-power-plant-electricity-costs-over-15-cents-per-kilowatt-hour-at-launch#:~:text=Due%20to%20the%20price%20increases%20in%20the%20UK%2C,the%20International%20Economic%20Forum%20for%20Renewable%20Energies%20%28IWR%29
[40] Department for Energy Security and Net Zero, Electricity Generation Costs 2023
[42] Life Cycle Assessment of electricity from Torness nuclear power plant development EDF, May 2022
[43] GHG
emissions and energy performance of offshore wind power. Hanne Lerche Raadal et al, June 2014
[44] Environmental impacts of solar photovoltaic systems: A critical review of recent progress and future outlook. Muhammad Tawalbeh et al, March 2021
[46] https://theconversation.com/nuclear-power-is-set-to-get-a-lot-safer-and-cheaper-heres-why-62207?utm_medium=email&utm_campaign=Latest%20from%20The%20Conversation%20for%20April%2012%202017%20-
[47] https://www.gov.uk/government/publications/uk-radioactive-waste-and-material-inventory-2022/uk-radioactive-waste-inventory-2022
[50] Attention is drawn to government decisions in Belgium, Germany, Japan, Scotland and Switzerland to close or phase out nuclear power plants after the Fukushima accident in 2011.
[51] Digest of UK Energy Statistics Annual data for UK,2023, DESNEZ, UK